City of Rocky River, Ohio

Public Works - Safety Service Department

The Office of Public Works is responsible for the successful execution of biddable and non-biddable projects throughout the City of Rocky River.

Click here to visit City Surplus Auction to view local items available at auction.

Black and White photo of Bradstreet's Landing

Current Bid Packages and Proposals

Construction Updates

May 9, 2025 Construction Update

Current Construction Projects

Rocky River Park Storm Sewer and Sidewalk Project

RMH Concrete and Foundations, Inc. has begun an important improvement project to preserve the stability of the stepped wall at the park. Inspection performed by a geotechnical firm in 2023 reported that water running between the curb and parking lot may be contributing to the toe of the stepped hillside heaving. In 2023, we contracted with GeoTech Services, Inc. to have columns of compaction grout installed every five (5) feet behind the wall. The contractor drove steel pipes and injected High Density Polyurethane grout through the pipes to compact and stabilize loose fill material and fill any voids.

This project entails installing a catch basin and new curb on the west side of the parking lot at Rocky River Park to aid in protecting the hillside from water infiltration off the parking lot between the pavement and curb. The catch basin will drain under the parking lot to the bioretention basin in the center of the parking lot for infiltration. The plans for the project were reviewed and approved by representatives from Cuyahoga Soil and Water Conservation District.

Once the catch basin is installed, new sidewalk will be added between the curb and the top of the wall, and an ADA compliant curb ramp will be installed on the north end of the sidewalk. The Recreation Department has plans to install new fencing that is consistent with the new stairs to replace the white vinyl fencing once this project is complete.

Please use caution around the work zone. The project is expected to be complete by the first of July.

Parklane Drive Watermain Replacement Project

City Council passed legislation on March 24, 20225, to enter a contract with Fabrizi Trucking and Paving Company, Inc. for the Parklane Drive Water Main Replacement Project in an amount not to exceed $942,851.00, which includes the election to include an alternate of $29,280.00 for additional catch basin replacements.  Many of the existing catch basins on the street were an old design which created difficulties for replacement grate. The City received four (4) bids on January 31, 2025, and the bid by Fabrizi was $41,772.50 lower than the second lowest bid including Alternate 1.

This project entails new water mains and connections to the edge of the right-of-way. Service lines to residential properties will also be replaced upon identification of any lead or galvanized water connections to homes on Parklane Drive, west of Wooster Road.  The water main replacement is being funded as part of Cleveland Division of Water’s Suburban Water Main Renewal Program in an amount of $401,160.  Upon completion of the water main work, the street will be resurfaced with apron and curb repairs, full depth concrete repairs, and an asphalt overlay.

As of May 9, 2025, the watermain installation has been completed with service lines and valves being installed on May 12, 2025. Following completion of the private water connections, the contractor will move into the pavement restoration phase of the project.

Completion date (per the contract) is Thursday, July 10, 2025.

Upcoming Construction Projects

Buckingham Road, Argyle Oval, and Arundel Road Sewer Replacement Project

The Buckingham Road, Argyle Oval & Arundel Road Sewer Replacement Project is for the replacement of almost 2,000 linear feet of inverted storm and sanitary sewer on public property, as well as the replacement of water mains and connections for all properties, and pavement resurfacing.

The public project area directly services 45 homes and lies within Sewershed 4 in the City of Rocky River.  This area was identified as a necessary location for rehabilitation to reduce infiltration and inflow (I/I) as part of our most recent hydraulic study performed in response to an Administrative Order on Consent by the US Environmental Protection Agency (USEPA) requiring the closure of two remaining Sanitary Sewer Overflows (SSOs) within the City.  Sewershed 4 serves 356 properties within approximately 134 acres of the City and contains one of the two remaining sanitary sewer overflows (SSO’s), SSO No.302, located at Falmouth Drive and Beach Cliff Boulevard, adjacent to the project location.   

Much of the sanitary and storm infrastructure supporting Sewershed 4 is beyond its useful life, in some cases upwards of 100 years old. Coupled with the aging infrastructure, many of the oldest homes in the community are concentrated in Sewershed 4. Portions of sewer system in Sewershed 4 were constructed as over/under sewers, where the sanitary sewer pipe was constructed in the same trench as the storm sewer. Within the manhole, the two sewers are generally only separated by a metal plate which may leak or become dislodged, causing the storm water to flow into the sanitary sewer.  This construction technique, which is unique to northeast Ohio, further contributes to I/I problems, particularly as the infrastructure ages. The additional volume of storm water adds to the volume of the sanitary system, and travels to the wastewater treatment plant for treatment, or during high flow events, may be released directly into the storm system, through outfalls into Lake Erie.  These overflows are a serious risk to the water quality of Lake Erie and to the health of the public and wildlife who rely on the lake as a natural resource.

The City of Rocky River has worked diligently to perform sewer rehabilitation and has successfully closed 12 of the 14 remaining SSO’s through public works projects.  In September of 2009, the USEPA issued Administrative Orders requiring the removal of three (3) SSOs as well as directing the City to perform a City-wide Sanitary Sewer Evaluation Study (SSES). During the intervening period, one of the three SSOs was removed, and SSES Phase I was conducted for Sewersheds 4, 5, and 12. 

Sewershed 4 was included in the first phase of the SSES due to the location of SSO No. 302 within its boundary. The SSES investigation included collection system inspections and cleaning, mainline and private property dye testing, flow monitoring, hydraulic modeling and improvement planning for each of the selected sewersheds and has been the basis the City’s calculated approach to the planning and implementation of sewer rehabilitation projects in the community.

The project is expected to cost approximately $5,575,000 with $2,520,000 paid by grant funding awarded by federal Community Project Funding that was awarded in 2022 and $639,930 awarded as part of Cleveland Division of Water’s Suburban Water Main Renewal Program. Construction is expected to commence in the fall of 2024 and be completed late 2025.

Please note that while this page is updated regularly, more current information may be available. Please reach out to the Office of the Director of Public Safety-Service at (440) 331-0600 for the most up to date information on all of our past, present, and future projects.

We’re here for you!

Please let us know if there are necessary repairs, problems or concerns you have regarding public works and infrastructure throughout the City of Rocky River.

Contact Us:

Office of the Director of Public Safety-Service | safetyservice@rockyriverohio.gov | 440.331.0600

Rocky River City Hall | 21012 Hilliard Boulevard, Rocky River, Ohio 44116

Rich Snyder

Director of Public Safety-Service

rsnyder@rockyriverohio.gov | 440.895.2581

Maureen Nakonek

Safety-Service Coordinator

mnakonek@rockyriverohio.gov | 440.331.0600 ext. 2011

Mark Filipic

Public Works Coordinator

mfilipic@rockyriverohio.gov | 440.331.0600 ext. 2025